Numerous violations and shortcomings revealed in the activities of the Belarusian regional capital construction management

Numerous violations and shortcomings revealed in the activities of the Belarusian regional capital construction management
  • 10 October, 2025

    The regional unit of the State Control Committee of the Republic of Belarus during the inspection of the municipal unitary subsidiary of the region revealed illegal receipt of budget funds in the amount of 345 thousand Belarusian rubles, misuse of funds of equity holders
    in the amount of more than 300 thousand Belarusian rubles, untimely processing of budget advances in the amount of about 600 thousand Belarusian rubles.

    In addition, the inspection established overestimations of the cost of construction and installation works carried out at the expense of the budget, payment of a premium to the head of the enterprise if there is a debt for payments to the budget, illegal attribution to the costs of using personal cars of employees, non-allocation of budget funds for the construction of engineering and transport infrastructure.

    Also, according to the proposals made by the regional unit of the State Control Committee of the Republic of Belarus, the cost of building facilities is reduced by more than 3 million Belarusian rubles due to the exclusion of excessive work and costs from the design and estimate documentation (for the excessive construction of buildings and structures, engineering networks, etc.).

    According to the results of the inspection, the enterprise and 4 of its officials were brought to administrative and disciplinary responsibility.

    The recovery of illegally received budget funds is under control.